Monday, October 31, 2011 at 5:21 AM
CHI-D cloud

5:40 GMT 30.10.11

Dear Customers

We are having issue on Storage Network Chi-D cloud, this cause a IO load to all VPS’s. Our engineers working on this issue and will try to sort it out as soon as it possible.

UPDATE 06:25 GMT All servers in queue for startup, but due to IO high load startup process is slow. By now 10%  of SAN synchronisation process has been completed.

UPDATE 08:20 GMT 14% of synchronisation process completed at the moment.

UPDATE 10:20 GMT 16% of synchronisation process completed at the moment.

UPDATE 12:10 GMT 19,1% of synchronisation process completed at the moment.

UPDATE 14:15 GMT 22,3% of synchronisation process completed at the moment.

UPDATE 17:00 GMT 28,3% of synchronisation process completed at the moment.

UPDATE 18:05 GMT 30,2% of synchronisation process completed at the moment.

UPDATE 19:00 GMT 31,9% of synchronisation process completed at the moment.

UPDATE 20:00 GMT 33,9% of synchronisation process completed at the moment.

UPDATE 21:47 GMT 37,5% of synchronisation process completed at the moment.

UPDATE 23:00 GMT 39,7% of synchronisation process completed at the moment.

UPDATE 00:00 GMT 42% of synchronisation process completed at the moment.

01.11.11

UPDATE 01:30 GMT 44,5% of synchronisation process completed.
UPDATE 03:00 GMT 47,8% of synchronisation process completed.
UPDATE 05:45 GMT 53,1% of synchronisation process completed.
UPDATE 08:30 GMT 58,5% of synchronisation process completed.
UPDATE 11:20 GMT 64,2% of synchronisation process completed.
UPDATE 14:39 GMT 70,6% of synchronisation process completed.
UPDATE 18:00 GMT 77,3% of synchronisation process completed.
UPDATE 19:30 GMT 80,2% of synchronisation process completed.
UPDATE 20:35 GMT 82.3% of synchronisation process completed.
UPDATE 21:30 GMT 84.1% of synchronisation process completed.
UPDATE 22:30 GMT 86.4% of synchronisation process completed.
UPDATE 23:50 GMT 88.8% of synchronisation process completed.

02.11.11

UPDATE 01:00 GMT 91% of synchronisation process completed.
UPDATE 02:15 GMT 93.6% of synchronisation process completed.
UPDATE 03:20 GMT 95.9% of synchronisation process completed.
UPDATE 04:30 GMT 98.2% of synchronisation process completed.
UPDATE 05:30 GMT Synchronization has completed successfully.